Rubin Construction activity on Cerro Pachón
Construction activity on Cerro Pachón continues to expand, with approximately 40 people working on the summit each day last week. That will increase this week with the restart of the team installing critical telescope utilities. The contracted team for the dome is now about 20 people who are focused on getting the dome enclosed before the TMA team arrives in January. The dome cladding is going up fast!
Créditos:Rubin Obs/NSF/AURA
About the Image
Id: | 20201112_162406 |
Tipo: | Photographic |
Release date: | 27 de Julio de 2021 a las 10:43 |
Size: | 4032 x 2268 px |
Sobre el Objeto
Nombre: | Simonyi Survey Telescope |
Categoría: | Vera C. Rubin Observatory |